In the end it all comes down to facts... and what we see vs what we hear.
The NY Canal Corporation started clearing what they termed as "Unsafe Embankment Dams" in our area as part of a Project called EERP, the Earthen Embankment Restoration Project. It started from the Western end of the main Erie Canal in Buffalo and worked it's way to Brockport. The NYCC was very exact about what they wanted to fix, spoke with the public about their plans in several meetings and outlined why this embankment clearing work needed to be done.. they stated:
1) There were Earthen Dams under all those trees lining the Erie Canal in our area...and those dams were Unsafe.
2) The hidden Earthen Dams were being damaged by the woody overgrowth and this type of covering was not allowed on dams of this type
3) Many of these Earthen Dams were nearing 100 years old & had never undergone a proper earthen dam inspection
4) Neighbors of the Erie Canal, living below the dams, were in danger of potential flood due to embankment breaching if the trees remained.
Now some people believed the Canal Management & Project Leaders, and some did not. Some worked with the Canal Corporation on "good faith" thinking they would not be untruthful about Public Safety, and some folks scoffed at safety and have worked against the Embankment safety work from Day #1. But the real proof is is what was said and whether or not it really was the truth.
The New York Canal Corporation submitted a package that included a number set of work zones... that we now know are Earthen Dams.

They also had how large the clearing work would be and the State Safety Level Risk Rating (SLRR) for each Embankment.

They included Maps for these unsafe dams that needed repair

And when they started to clear the embankments off low and behold...they DID find that there were Earthen Dams underneath all that woody vegetation. Here's a section of Dam #37 just East of the Village of Brockport where houses within 50' of the Top of the Dam were virtually invisible. Dam 37 is approximately 1.5 miles long with heights of 18-22 feet above neighborhoods to the North

So as you can see the NY Canal Corporation was spot on with their assessment of the Public Safety Nightmare the Erie Canal had become.
But some still ignored the warnings and stopped the progress of the original EERP Project... but NOT before about 40 Dams were cleared. Those dams are listed on their original project task list, along with about a dozen dam zones that were moved to the new Earthen Embankment Integrity Program. That new program will look at clearing BOTH sides of the waterway and it's apertunate structures, for the entire length of the system...regardless of if the embankment is raised or landcut. Tree clearing is going to happen for the sake of public safety along the canal trail, and the safety of those living below the earth dams sections.
I will document these original 40 EERP Dams in this post.. starting at Dam # 1 just west of Medina, near the old Fruit Ave "Lowbridge" crossing. If nothing more it gives EACH of you a chance to see what Earthen Dams are supposed to look like, and proves those original f safety points made by the Canal Corporation...
It's about Inspection & Safety at the end of the day, regardless of what some may say or think about Erie Canal Embankments